Archive for the ‘Reception Building Construction Photos’ Category

Finished

Monday, July 21st, 2008
Finished

The offices and reception were fitted out with furniture, computers and phones in May. After the inevitable new computer teething problems and the move from the old offices Marg is very happy with her new facility. Tony and Julie are pleased to have their house back.

Fixtures and fittings

Thursday, May 15th, 2008
Fixtures and fittings

The kitchen and toilets are fitted.

Inside

Tuesday, March 25th, 2008
Inside

The timber frame interior rooms are fitted along with the electrics, lighting, airconditioning, floor tiles and glass doors and windows. All the timber fames and skirting came raw and had to be stained and sealed. The walls and gyprock ceiling all had to be painted.

 

Ready for the Top Coat.

Saturday, February 23rd, 2008
Ready for the Top Coat.

The coloured external top coat is applied.

The helpers tidy up

Friday, February 22nd, 2008
The helpers tidy up

The under coat undergoes some expert fine tuning from Tony before the external coloured top coat is applied.

On goes the render.

Wednesday, February 20th, 2008
On goes the render.

Render is sprayed, sealing the bales inside and out.

The Plasterers arrive

Wednesday, February 20th, 2008
The Plasterers arrive

The window frames and roof are protected from the render spraying machine.

The walls go up

Thursday, February 7th, 2008
The walls go up

The walls are finished in a couple of days. Stacking the walls with whole bales was quick and easy. Blocking around the doors and windows with customized bale sections took longer.

Ready for the bales.

Wednesday, February 6th, 2008
Ready for the bales.

The roof went on and the timber boxing installed ready for the straw bale outer walls to be fixed.

Up goes the frame

Tuesday, January 29th, 2008
Up goes the frame

The steel frame is raised and bolted in two days.